Contractor Execution Recap

10 min
6/6

Key Takeaways

  • Weekly management cycles with five metrics provide early warning.
  • CO negotiation using contract rates saves 10-30%.
  • Punch list and retainage require persistent follow-through.
  • GC coordination value shows during multi-challenge scenarios.

Review of execution management from Track 2.

Execution Recap

Weekly cycles monitor Progress, Quality, Cost. EVM detects variances early. CO markups 30-50% vs. 15-25% bid—negotiate with contract rates. Punch lists average 30-80 items. GC networks justify their 15-25% margin during crises.

Key Takeaways

  • Weekly management cycles with five metrics provide early warning.
  • CO negotiation using contract rates saves 10-30%.
  • Punch list and retainage require persistent follow-through.
  • GC coordination value shows during multi-challenge scenarios.

Common Mistakes to Avoid

Not conducting a formal post-project review

Consequence: Same contractor management mistakes repeated on every project without improvement

Correction: Conduct a formal review within 30 days of project completion: evaluate schedule accuracy, budget accuracy, quality, and communication

Test Your Knowledge

1.SPI of 0.85 means?

2.Average CO markup vs. bid work?

3.Average punch list items?