Skip to main contentSkip to navigationSkip to footer

Development Pro Forma and Draw Schedule Modeling

13 minPRO
2/6

Key Takeaways

  • Development budgets have hard costs (60-70%), soft costs (15-25%), and financing costs (10-15%) plus contingency.
  • Construction interest carry is often underestimated and can reach 10-15% of total development budget.
  • Draw schedules must be modeled monthly to accurately calculate cumulative interest on funds disbursed.
  • Lease-up modeling projects monthly occupancy growth from zero to stabilization (90-95% occupancy).

Ground-up development and major renovation projects require a fundamentally different financial model than stabilized acquisitions. Instead of projecting from existing income, development models start with zero revenue and build toward stabilized occupancy over a construction and lease-up timeline. This lesson covers the development budget, construction draw schedule, interest carry, and the transition to stabilized operations.

Scenario 1
Basic

The Development Budget

A development budget has three major components. Hard Costs include all physical construction: site work, foundation, structure, exterior envelope, interior finishes, mechanical/electrical/plumbing (MEP), and landscaping. Hard costs typically represent 60-70% of total development cost. Soft Costs include architecture, engineering, permits, legal, accounting, insurance during construction, property taxes during construction, marketing, and developer overhead. Soft costs typically represent 15-25% of total costs. Financing Costs include loan origination fees, construction interest (interest carry), commitment fees, and exit financing costs. The construction interest carry—interest that accrues during construction when there is no revenue to cover it—is often the most underestimated cost, potentially reaching 10-15% of the total development budget for longer construction timelines.

Cost Category% of TotalKey ComponentsEstimating Method
Hard Costs60-70%Construction, site work, finishesContractor bids, RS Means
Soft Costs15-25%A&E, permits, legal, insuranceProfessional quotes, % of hard costs
Financing10-15%Interest carry, origination, feesCalculated from draw schedule
Contingency5-10%Unknown conditions% of hard + soft costs

Development budget structure

Scenario 2
Moderate

Construction Draw Schedule

The draw schedule projects how construction loan funds are disbursed over the construction period. Unlike an acquisition loan where the full amount is funded at closing, construction loans are drawn in stages as work is completed. A typical 18-month construction project might have the following draw pattern: Month 1-3 (site work, foundation): 15% of hard costs. Month 4-8 (structure, framing, MEP rough-in): 35% of hard costs. Month 9-14 (exterior, interior finishes): 35% of hard costs. Month 15-18 (finishes, punch list, landscaping): 15% of hard costs. The draw schedule determines interest carry—you only pay interest on funds actually drawn, so front-loaded draws increase total interest cost. Model draws monthly to accurately calculate cumulative interest.

Loading interactive chart...
Scenario 3
Complex

Lease-Up to Stabilization

After construction completion, the property enters the lease-up phase with zero occupancy. Lease-up pace depends on market conditions, property type, and marketing effort—typical multifamily lease-up is 10-20 units per month in strong markets. Model the lease-up monthly: each month's revenue equals the number of occupied units multiplied by rent, with concessions applied to early movers (first 30-50% of units may receive one month free or reduced rent). Operating expenses begin at construction completion and ramp up as occupancy increases (utilities scale with occupancy, management fees scale with revenue, but insurance and taxes are full-cost from day one). Stabilization is typically defined as 90-95% occupancy maintained for 3 consecutive months—at this point, the property qualifies for permanent financing to replace the construction loan.

Watch Out For

Using annual averages for construction interest instead of monthly draw-by-draw calculations

Can understate interest carry by 20-40%, blowing through the financing budget

Fix: Model draws monthly: each month's interest = cumulative balance drawn x monthly rate

Projecting linear lease-up instead of an S-curve pattern

Overestimates early revenue (first units lease slowly due to construction disruption and limited amenities)

Fix: Model an S-curve: slow initial lease-up, accelerating mid-phase, tapering as the last units fill

Omitting lease-up concessions from the revenue model

Overstates effective revenue during lease-up by 5-10%, inflating projected stabilized cash flow timing

Fix: Model concessions explicitly: 1-2 months free rent for the first 30-50% of units leased

Key Takeaways

  • Development budgets have hard costs (60-70%), soft costs (15-25%), and financing costs (10-15%) plus contingency.
  • Construction interest carry is often underestimated and can reach 10-15% of total development budget.
  • Draw schedules must be modeled monthly to accurately calculate cumulative interest on funds disbursed.
  • Lease-up modeling projects monthly occupancy growth from zero to stabilization (90-95% occupancy).

Common Mistakes to Avoid

Using annual averages for construction interest instead of monthly draw-by-draw calculations

Consequence: Can understate interest carry by 20-40%, blowing through the financing budget

Correction: Model draws monthly: each month's interest = cumulative balance drawn x monthly rate

Projecting linear lease-up instead of an S-curve pattern

Consequence: Overestimates early revenue (first units lease slowly due to construction disruption and limited amenities)

Correction: Model an S-curve: slow initial lease-up, accelerating mid-phase, tapering as the last units fill

Omitting lease-up concessions from the revenue model

Consequence: Overstates effective revenue during lease-up by 5-10%, inflating projected stabilized cash flow timing

Correction: Model concessions explicitly: 1-2 months free rent for the first 30-50% of units leased

"Advanced Modeling: Development Pro Formas, Funds & Attribution" is a Pro track

Upgrade to access all lessons in this track and the entire curriculum.

Immediate access to the rest of this content

1,746+ structured curriculum lessons

All 33+ real estate calculators

Metro-level data across 50+ regions

Test Your Knowledge

1.Why must development pro formas use monthly rather than annual periods?

2.What is a draw schedule in development modeling?

3.What does "lease-up to stabilization" model in a development pro forma?

Was this lesson helpful?

Your feedback helps us improve the curriculum.

Share this