Key Takeaways
- Development budgets have hard costs (60-70%), soft costs (15-25%), and financing costs (10-15%) plus contingency.
- Construction interest carry is often underestimated and can reach 10-15% of total development budget.
- Draw schedules must be modeled monthly to accurately calculate cumulative interest on funds disbursed.
- Lease-up modeling projects monthly occupancy growth from zero to stabilization (90-95% occupancy).
Ground-up development and major renovation projects require a fundamentally different financial model than stabilized acquisitions. Instead of projecting from existing income, development models start with zero revenue and build toward stabilized occupancy over a construction and lease-up timeline. This lesson covers the development budget, construction draw schedule, interest carry, and the transition to stabilized operations.
The Development Budget
A development budget has three major components. Hard Costs include all physical construction: site work, foundation, structure, exterior envelope, interior finishes, mechanical/electrical/plumbing (MEP), and landscaping. Hard costs typically represent 60-70% of total development cost. Soft Costs include architecture, engineering, permits, legal, accounting, insurance during construction, property taxes during construction, marketing, and developer overhead. Soft costs typically represent 15-25% of total costs. Financing Costs include loan origination fees, construction interest (interest carry), commitment fees, and exit financing costs. The construction interest carry—interest that accrues during construction when there is no revenue to cover it—is often the most underestimated cost, potentially reaching 10-15% of the total development budget for longer construction timelines.
| Cost Category | % of Total | Key Components | Estimating Method |
|---|---|---|---|
| Hard Costs | 60-70% | Construction, site work, finishes | Contractor bids, RS Means |
| Soft Costs | 15-25% | A&E, permits, legal, insurance | Professional quotes, % of hard costs |
| Financing | 10-15% | Interest carry, origination, fees | Calculated from draw schedule |
| Contingency | 5-10% | Unknown conditions | % of hard + soft costs |
Development budget structure
Construction Draw Schedule
The draw schedule projects how construction loan funds are disbursed over the construction period. Unlike an acquisition loan where the full amount is funded at closing, construction loans are drawn in stages as work is completed. A typical 18-month construction project might have the following draw pattern: Month 1-3 (site work, foundation): 15% of hard costs. Month 4-8 (structure, framing, MEP rough-in): 35% of hard costs. Month 9-14 (exterior, interior finishes): 35% of hard costs. Month 15-18 (finishes, punch list, landscaping): 15% of hard costs. The draw schedule determines interest carry—you only pay interest on funds actually drawn, so front-loaded draws increase total interest cost. Model draws monthly to accurately calculate cumulative interest.
Lease-Up to Stabilization
After construction completion, the property enters the lease-up phase with zero occupancy. Lease-up pace depends on market conditions, property type, and marketing effort—typical multifamily lease-up is 10-20 units per month in strong markets. Model the lease-up monthly: each month's revenue equals the number of occupied units multiplied by rent, with concessions applied to early movers (first 30-50% of units may receive one month free or reduced rent). Operating expenses begin at construction completion and ramp up as occupancy increases (utilities scale with occupancy, management fees scale with revenue, but insurance and taxes are full-cost from day one). Stabilization is typically defined as 90-95% occupancy maintained for 3 consecutive months—at this point, the property qualifies for permanent financing to replace the construction loan.
Watch Out For
Using annual averages for construction interest instead of monthly draw-by-draw calculations
Can understate interest carry by 20-40%, blowing through the financing budget
Fix: Model draws monthly: each month's interest = cumulative balance drawn x monthly rate
Projecting linear lease-up instead of an S-curve pattern
Overestimates early revenue (first units lease slowly due to construction disruption and limited amenities)
Fix: Model an S-curve: slow initial lease-up, accelerating mid-phase, tapering as the last units fill
Omitting lease-up concessions from the revenue model
Overstates effective revenue during lease-up by 5-10%, inflating projected stabilized cash flow timing
Fix: Model concessions explicitly: 1-2 months free rent for the first 30-50% of units leased
Key Takeaways
- ✓Development budgets have hard costs (60-70%), soft costs (15-25%), and financing costs (10-15%) plus contingency.
- ✓Construction interest carry is often underestimated and can reach 10-15% of total development budget.
- ✓Draw schedules must be modeled monthly to accurately calculate cumulative interest on funds disbursed.
- ✓Lease-up modeling projects monthly occupancy growth from zero to stabilization (90-95% occupancy).
Sources
- RSMeans/Gordian — Construction Cost Data(2025-01-15)
- Argus Software — Development Module(2025-01-15)
Common Mistakes to Avoid
Using annual averages for construction interest instead of monthly draw-by-draw calculations
Consequence: Can understate interest carry by 20-40%, blowing through the financing budget
Correction: Model draws monthly: each month's interest = cumulative balance drawn x monthly rate
Projecting linear lease-up instead of an S-curve pattern
Consequence: Overestimates early revenue (first units lease slowly due to construction disruption and limited amenities)
Correction: Model an S-curve: slow initial lease-up, accelerating mid-phase, tapering as the last units fill
Omitting lease-up concessions from the revenue model
Consequence: Overstates effective revenue during lease-up by 5-10%, inflating projected stabilized cash flow timing
Correction: Model concessions explicitly: 1-2 months free rent for the first 30-50% of units leased
"Advanced Modeling: Development Pro Formas, Funds & Attribution" is a Pro track
Upgrade to access all lessons in this track and the entire curriculum.
Immediate access to the rest of this content
1,746+ structured curriculum lessons
All 33+ real estate calculators
Metro-level data across 50+ regions
Test Your Knowledge
1.Why must development pro formas use monthly rather than annual periods?
2.What is a draw schedule in development modeling?
3.What does "lease-up to stabilization" model in a development pro forma?